§ 7.7.7. Public water supply systems; requirements.
All public water supply systems shall meet all of the following requirements:
(A)
Issuance of all permits required by the County Health Department and the State Department of Environmental Regulation as evidence of compliance with standards and regulations set by the State relating to public water supply systems.
(B)
Construction of an approved interim water treatment plant in accordance with the requirements of the County Health Department and the State Department of Environmental Regulation and approved by the City Engineer.
(C)
If the subject development would ordinarily require installation of water lines for connection to the City system, these water lines will still be required except that during the interim period while water wells are in use, these lines shall be used for fire protection purposes only. Connection to the City water supply system shall be by a method as approved by the City Engineer and the City Building Department.
(D)
Execution of an agreement between property owner and City for the operation, maintenance, and of the removal of any interim water treatment plant installed hereunder. The agreement shall be in form and content approved hereafter by resolution of the City Commission.
(E)
Receipt of a permit from the City Building Department, which shall be issued if applicant complied with conditions of divisions (A) through (D) of this section and has paid the proper permit fee.